Revision of Project Registration Validity and Extended Timeline for Statutory Compliances, in view of Covid 19 Pandemic


Issued by: MAHARERA | 02 April 2020

  • For all MahaRERA Registered projects where completion date, revised completion date or extended completion date expires on or after 15th March 2020, the period of validity for registration of such projects shall be extended by three months. MahaRERA shall accordingly issue project registration certificates, with revised timelines for such projects, at the earliest. 
  • Further, the time limits of all statutory compliances in accordance with the Real Estate (Regulation and Development) Act, 2016 and the rules and regulations made thereunder, which were due in March / April / May are extended to 30th June 2020.